Steel beams, composite metal deck, shear studs, mesh and lightweight concrete.
Layers, in order
| # | Layer | Thickness | Spacing |
|---|---|---|---|
| 1 | W8 steel beams | 8 1/4 in | at 72 in o.c. |
| 2 | 1 1/2 in composite metal deck | 1 1/2 in | |
| 3 | Headed shear studs | 3 1/2 in | at 12 in o.c. |
| 4 | Welded wire fabric | 1/8 in | |
| 5 | 4 in lightweight concrete | 4 in |
Build steps
- Erect the beams (Ironworker).
- Lay the deck (Ironworker).
- Weld the shear studs (Ironworker).
- Place the mesh (Concrete).
- Pour the slab (Concrete).